Respond to Discussion Responses

S M

Q1: Discuss what resources are most critical for most of the construction projects and how to incorporate the information into the schedule?

There are many ways to make the schedule more effective and they are, Project deliverables, Tasks required to complete the deliverables, Dependencies between tasks, Resources required to complete each task, Task durations and project deadline, Budget of the project, and Planned time for each resource. As well, for incorporate the schedule by monitoring and controlling the schedule and estimate the duration of each of the activities.

Respond

Q2: Discuss one disadvantage that you see in using a linear schedule for a multilevel building project?

The disadvantage of having a linear schedule for a multilevel building is that it will require to re-develop the schedule all the time. It becomes extremely detailed that making the network difficult for the user to visualize and manage even. The exact originals of graphical techniques are not clear and they may have multiple original. As well, the limitation of linear scheduling method is that it assumes that production rates are linear

Respond

M G

1. Discuss what resources are most critical for most of the construction projects and how to incorporate the information into the schedule?

To complete an activity, the CM needs to ensure 3 elements are provided in a timely manner:

Human resources – Meaning the corresponding qualified team needs to enter the site at the intended time.

Equipment – Either the appropriate team or the CM must procure the equipment that will facilitate . This not only refers to the power tools used for a job, but also refers to scaffolding, safety gear etc.

Materials – Meaning the actual construction materials used to build. This goes from steel and concrete to carpentry, flooring, and light fixtures.

Respond

2. Discuss one disadvantage that you see in using a linear schedule for a multilevel building project ?

While multilevel building projects are indeed quite predictable and repetitive, often they are filled with detailing. Other projects that typically employs Linear scheduling , such as highways and roads are heavy on structure but low on detailing such as interior finishes, carpentry etc.

This causes many smaller tasks that come from a multilevel building that need to be registered and accounted for on the linear schedule, making the schedule to become flooded with activities.

This can me it hard to understand and confusing to a team member. The information may not be as easy to access because of the formatting of the chart, as opposed to say a Gantt chart.

Respond

G G

1. Discuss what the recourses are most critical for most of the construction projects and how to incorporate the information into the schedule?

Virtually all projects have limited capacity or resources. Therefore, the success of a project is tied to how well the resources are managed and how well the project is scheduled. The traditional methods of project scheduling have been either the Critical Path Method (CPM) or the Gantt Chart. However, Critical Path Analysis is limited in its assumption the project has infinite capacity. A new method of project scheduling has been proposed the incorporates finite capacity of labor. capital equipment, facilities, and material into its scheduling formula. Resource scheduling incorporates decisions about capacity into the scheduling process using two methods:

Time: constrained and resources constrained. Time-constrained scheduling uses time factors as its critical variable, while resources-constrained focuses on the limited capacity of resources, with emphasis on resolving capacity overload problems.

Respond

Respond to

Discussion Responses

S M

Q1: Discuss what resources are most critical for most of the construction

projects and how to

incorporate

the information into the schedule?

There are many ways to make the schedule more effective and they are,

Project deliverables, Tasks

required to complete the deliverables, Dependencies between tasks, Resources required to complete

each task, Task durations and project deadline, Budget of th

e project, and Planned time for each

resource. As well, for incorporate the schedule by monitoring and controlling the

schedule and

estimate

the duration of each of the activities.

Respond

Q2: Discuss one

disadvantage

that you see in using a

linear schedule for a

multilevel

building

project?

The disadvantage of having a linear schedule for a multilevel building is that it will require to re

develop

the schedule

all the time. It becomes extremely detailed that making the network difficult for

the user to visualize

and manage even. The exact originals of graphical techniques are not clear and they

may have multiple original. As well, the limitation of linear scheduling method is that it assumes that

production rates are linear

Respond

M G

1. Discuss what resources are most critical for most of the constructi

on projects and how to incorporate

the information into the schedule?

To

complete an

activity,

the CM needs to ensure 3 elements are provided in a timely manner:

Human resources

Meaning the corresponding qualified team needs to enter the site

at the intended

time.

Equipment

Either the appropriate team or the CM must procure the equipment that will facilitate .

This not only refers to the power tools used for a

job

, but also refers to scaffolding, safety gear etc.

Materials

Meaning the actual construction materials used to build. This goes from steel and concrete

to carpentry, flooring, and light fixtures.

Respond

2. Discuss one disadvantage that you see in using a linear schedule for a multilevel building project ?

While multilevel building projects are indeed quite predictable and repetitive, often they are filled with

detailing. Other projects that typically employs Linear scheduling , such as highways and roads are heavy

on

structure but low on detailing such as

interior finishes, carpentry etc.

Respond to Discussion Responses

S M

Q1: Discuss what resources are most critical for most of the construction projects and how to

incorporate the information into the schedule?

There are many ways to make the schedule more effective and they are, Project deliverables, Tasks

required to complete the deliverables, Dependencies between tasks, Resources required to complete

each task, Task durations and project deadline, Budget of the project, and Planned time for each

resource. As well, for incorporate the schedule by monitoring and controlling the schedule and estimate

the duration of each of the activities.

Respond

Q2: Discuss one disadvantage that you see in using a linear schedule for a multilevel building project?

The disadvantage of having a linear schedule for a multilevel building is that it will require to re-

develop the schedule all the time. It becomes extremely detailed that making the network difficult for

the user to visualize and manage even. The exact originals of graphical techniques are not clear and they

may have multiple original. As well, the limitation of linear scheduling method is that it assumes that

production rates are linear

Respond

M G

1. Discuss what resources are most critical for most of the construction projects and how to incorporate

the information into the schedule?

To complete an activity, the CM needs to ensure 3 elements are provided in a timely manner:

Human resources – Meaning the corresponding qualified team needs to enter the site at the intended

time.

Equipment – Either the appropriate team or the CM must procure the equipment that will facilitate .

This not only refers to the power tools used for a job, but also refers to scaffolding, safety gear etc.

Materials – Meaning the actual construction materials used to build. This goes from steel and concrete

to carpentry, flooring, and light fixtures.

Respond

2. Discuss one disadvantage that you see in using a linear schedule for a multilevel building project ?

While multilevel building projects are indeed quite predictable and repetitive, often they are filled with

detailing. Other projects that typically employs Linear scheduling , such as highways and roads are heavy

on structure but low on detailing such as interior finishes, carpentry etc.

Applied Sciences
Architecture and Design
Biology
Business & Finance
Chemistry
Computer Science
Geography
Geology
Education
Engineering
English
Environmental science
Spanish
Government
History
Human Resource Management
Information Systems
Law
Literature
Mathematics
Nursing
Physics
Political Science
Psychology
Reading
Science
Social Science
Home
Homework Answers
Blog
Archive
Tags
Reviews
Contact
google+twitterfacebook
Copyright © 2021 HomeworkMarket.com

Order Solution Now

Our Service Charter

1. Professional & Expert Writers: Homework Discussion only hires the best. Our writers are specially selected and recruited, after which they undergo further training to perfect their skills for specialization purposes. Moreover, our writers are holders of masters and Ph.D. degrees. They have impressive academic records, besides being native English speakers.

2. Top Quality Papers: Our customers are always guaranteed of papers that exceed their expectations. All our writers have +5 years of experience. This implies that all papers are written by individuals who are experts in their fields. In addition, the quality team reviews all the papers before sending them to the customers.

3. Plagiarism-Free Papers: All papers provided by Homework Discussion are written from scratch. Appropriate referencing and citation of key information are followed. Plagiarism checkers are used by the Quality assurance team and our editors just to double-check that there are no instances of plagiarism.

4. Timely Delivery: Time wasted is equivalent to a failed dedication and commitment. Homework Discussion is known for timely delivery of any pending customer orders. Customers are well informed of the progress of their papers to ensure they keep track of what the writer is providing before the final draft is sent for grading.

5. Affordable Prices: Our prices are fairly structured to fit in all groups. Any customer willing to place their assignments with us can do so at very affordable prices. In addition, our customers enjoy regular discounts and bonuses.

6. 24/7 Customer Support: At Homework Discussion, we have put in place a team of experts who answer to all customer inquiries promptly. The best part is the ever-availability of the team. Customers can make inquiries anytime.